156.2 kWp photovoltaic system - Ground mounted
Balta Alba City Hall Project - Funded by the Modernization Fund
Installed power in panels: 156.2 kWp
Installed power in inverters: 150 kW
Equipment used
- Installed panels: 252 pcs. x Trina Solar Vertex N TSM-NEG19RC.20 620 Wp
- Inverters: 3 pcs. x Huawei SUN2000-50KTL-M3
- Metal structure on the ground;
- DTSU666-H three-phase energy measurement system
- All materials required for installation: ground connection under 1 Ohm, ABB lightning protection system, LES alternating current and telecommunications networks;
- Installation of usage system: 250 kVA 0.4/20 kV transformer, network of poles up to the connection point.